LON 02

Client

GBL

Location

London

Services

Ductwork

Value

£2m Completed Works

IDSL have successfully completed all works on the LON 02 Project for GBL.

The Lon 02 Data Hall Project consisted of ductwork systems on the Ground, First, Second Floors and Roof. The IDSL programme dates for all 3 phases of work are summarised as follows:

  • Phase 1 – July 2022 to Feb 2023
  • Phase 2 – October 2022 to September 2023
  • Phase 3 – May 2023 to June 2024

IDSL completed all 3 phases on time and within budget.

IDSL are now back on site carrying out client post contract instructions that consist of installing small sections of ductwork off of CRAH units in various locations.