Ilona Rose House

Location

London

Services

Ducting

Value

£485K

Client

MJL

The Ilona Rose House Project consists of 9 floors and 4 Basement Levels. The Build of the Project is in its early stages and only the Basement Levels and Core of the building has been constructed to date. MJL are supplying the main plant and are free-issuing this to IDSL to install.

The IDSL scope of works is to install all of the Galvanised Ductwork on the Ilona Rose House Project. Fire Protection have been appointed by MJL to carry out the supply and install of Fire Rated Ductwork.

As a result, there are numerous interfaces between Galvanised and Fire Rated Ducts throughout the building. Demarcation Drawings have been submitted and the finalised scope of works for each package has been agreed by MJL, IDSL and FPL. Regular workshop meetings are being held to confirm handings of MSFDs required.

MJL have issued a combined services Installation Programme that IDSL are working to and monitoring against.

Site offices are not available yet as they are still being constructed.

IDSL works on Basement Level B4 have now commenced.

RoSPA-2024-Gold-sml Achilles Construction Line Gold Member CHAS Elite CCS_Logo_RGB_Featured_Image ISO 9001 Badge ISO-14001-logo ISO-45001-logo 114746_Daikin_D1_Plus_Logo_Main_RGB MITSUBISHI-ELECTRIC-BUSINESS-SOLUTIONS-PARTNER MITSUBISHI-HEAVY-INDUSTRIES cyberessentials_certification mark_colour LPCB Logo - White FIRAS Logo IFE_Affiliate Organisation_2024 BAB Logo