Skip to Content

Holborn Viaduct (Work in progress)

Client

Multiplex

Location

London

Services

Full turnkey package

IDSL appointed to deliver full turnkey package for the shell & core works at Holborn Viaduct, a new build commercial building. 

The new office building consists of 2 basement levels, ground, 10 upper floors to Holborn Viaduct and 12 upper floors to Farringdon Street including a roof plant level.  

Early engagement to undertake design verification of Hilson Moran intent including CDP of Smoke Clearance, Stair pressurisation and Fire Strategy.

Full Procurement of all plant and equipment including associated specialist sub-contractors.

Scope of Works below (not limited to):

  • GSS Ductwork
  • Fire Rated Ductwork
  • Thermal & Fire Rated Insulation
  • All Dampers (Smoke Control, Motorised Fire)
  • Decoder Loop Wiring 
  • Smoke Clearance / Stair Pressurisation
  • Air Handling Units (21)
  • Smoke Fans, Supply & Extract Fans (13)
  • MVHR Units (2)
  • Attenuators (135)
  • VAV Units (36)
  • Grilles & Diffusers
  • Durasteel
  • Commissioning
  • Plant Handling & Positioning 
  • BIM Modelling